Q1. What is a Solar Photovoltaic (SPV) System?
Ans A SPV system consists of a Photovoltaic Array mounted on a Stand, Batteries, CCU, and other required equipments depending upon the size and requirement of power and current.
 
Q2. How does it work?
Ans The Photovoltaic Array converts the solar energy into electricity, which is used for running the electrical equipments. The electricity produced either stored in the Battery bank or directly used for running the electrical equipment.
 
Q3. What does it save you?
Ans
  • It operates on the freely available solar energy. Thus saves expenditure on diesel & electricity.
  • No fear of power cuts or scarcity of diesel.
  • It is trouble free, pollution free, has a long life and is reliable.
  • Unlike a diesel pump set, it does not produce noise.
  • It is easy to handle and operate.
  • The cost of operation and maintenance is negligible.
  •  
    Q4. What is the Technology used in SPV Systems?
    Ans Solar cell is a primary device for Solar Photovoltaic systems since it converts solar radiation into electricity. Solar PV cells are made by fine sheets of silicon wafers, cutted in the required shape. The technology is mainly based on Monocrystalline silicon or polycrystalline technology. Number of such SPV cells are coupled in series and (or) parallel connection to design a SPV Module of required Power. These modules can be further coupled to form SPV array, to get desired power output to run the electrical appliances such as solar home systems, street lighting systems, small capacity SPV power plants, solar generators, building integrated photovoltaic (BIPV) systems and solar lanterns.
    The Photovoltaic Array converts the solar energy into electricity, which is used for running any electrical appliances or can stored in a battery.
    The system components of SPV Water Pumping System are:
  • PV Array
  • Battery Bank
  • Interface Electronics
  • Connecting Cables & Switches
  • Support Structure & Tracking System
  • Charge Controller Unit.
  • Electrical loads, such as, fans, lights, TV, etc.
  •  
    Q5. Who are eligible to own a Solar Photovoltaic System under the Scheme?
    Ans An individual, non-governmental organization, cooperative society, corporate body, institution and Govt. Dept. etc.
     
    Q6. What are the various SPV Systems eligible under the MNES Programme?
    Ans.
  • Solar Lantern.
  • Solar Home System.
  • Street Lighting System.
  • Small Capacity SPV Power plants.
  • Solar Generators.
  • Building integrated Photovoltaic (BIPV) Systems.
  •  
    Q7. What are the financing norms under interest subsidy schemes?
    Ans.
    S.NO Feature Implementation through IREDA
    1 Eligible categories of beneficiaries All categories of users including intermediaries and commercial organizations
    2 Rate of Interest 7% (commercial borrowers who can claim depreciation benefits)

    5% (individuals and other organizations)

    Financial intermediaries who borrow funds from IREDA for on – lending at 5% or 7% rate of interest will be charged an interest rate of 2.5% or 4.5% respectively by IREDA. Such intermediaries will not be able to claim depreciation benefit and the on-lending arrangement will not be treated as a lease arrangement.
    3 Loan period 3 Yrs
    4 Moratorium 1 Year
    5 Amount of loan 80% of the cost of the project
    6 Upper Limits for a loan No Limit
    7 Service Charges 1% of the loan disbursed
    8 System Covered All types of SPV Systems except solar pumps. Loans will not be provided at subsidized rates for systems that are available with capital subsidy. With the exception of solar generators for which both subsidies and soft loans will be available.
    9 Eligible Suppliers Only those SPV systems and power plants, which confirm to the MNES specifications & guidelines for 2001 – 02 or 2002 – 03 programmes and have obtained test certificates form SEC / Other Authorized Test Centers will be eligible for supply and other benefits under this scheme .
     
    Q8. What are the eligible models under interest subsidy scheme?
    Ans.  For Solar Lantern.

     
    S.NO Models Lamp Battery Capacity At C/20 Rate PV Module Rating
    1 MODAL I-A CFL 5W 12V, 7AH 8 to 9.9 Wp
    2 MODAL I-B CFL 5W 12V, 7AH 10 to 11.9 Wp
    3 MODAL II-A CFL 7W 12V, 7AH 10 to 11.9 Wp
    4 MODAL II-B CFL 7W 12V, 7AH 12 to 14 Wp
    5 MODAL III-A CFL 5W 6V, 14AH 8 to 9.9 Wp
    6 MODAL III-B CFL 5W 6V, 14AH 10 to 11.9 Wp
    7 MODAL IV-A CFL 7W 6V, 7AH 10 to 11.9 Wp
    8 MODAL IV-B CFL 7W 6V, 7AH 12 to 14 Wp
       
    For Solar Home Systems:
     

     

    MODEL

    Component

    Specifications

    Average Hours of Operation/ Day

    1

    PV Module

    1x18 Wp under STC

    1 Light, 3 – 4 Hrs.

    Lamp

    1xCFL (9W/11W)

     

    Battery

    1x12V, 20AH. Tubular Plate.

     

    Others Components

    Control electronics. Module mounting hardware. Battery box. Inter connecting wires. Swiches. Operation, instruction and maintenance manual.

     

    2

    PV Module

    1x37 Wp under STC

    2 Lights, 3 – 4 Hrs.

    Lamp

    2xCFL (9W/11W)

     

    Battery

    1x12V, 40AH. Tubular Plate.

     

    Others Components

    Control electronics. Module mounting hardware. Battery box. Inter connecting wires. Swiches. Operation, instruction and maintenance manual.

     

    3

    PV Module

    1x37 Wp under STC

    1 Light - 1 – 2 Hrs., 1 Fan – 1-2 Hrs.

    Lamp

    1xCFL (9W/11W)

     

    Fan

    1xDC Fan (with wattage less than 20W)

     

    Battery

    1x12V, 40AH. Tubular Plate.

     

    Others Components

    Control electronics. Module mounting hardware. Battery box. Inter connecting wires. Swiches. Operation, instruction and maintenance manual.

     

    4

    PV Module

    2x37 Wp or 1x74 Wp under STC

    2 Light - 2 – 3 Hrs., 1 Fan – 2-3 Hrs.

    Lamp

    2xCFL (9W/11W)

     

    Fan

    1xDC Fan (with wattage less than 20W)

     

    Battery

    1x12V, 75AH. Tubular Plate.

     

    Others Components

    Control electronics. Module mounting hardware. Battery box. Inter connecting wires. Swiches. Operation, instruction and maintenance manual.

     

    5

    PV Module

    2x37 Wp or 1x74 Wp under STC

    4 Lights – 3-4 Hrs.

    Lamp

    4xCFL (9W/11W)

     

    Battery

    1x12V, 75AH. Tubular Plate.

     

    Others Components

    Control electronics. Module mounting hardware. Battery box. Inter connecting wires. Switches. Operation, instruction and maintenance manual.

     

     

             Notes
  •     All models will have a socket to provide power for 12V DC TV set, which is purchased separately.
  •     Small white LED may be provided as an optional feature, with an independent switch.
  •  
    For Street Lighting Systems:
     
      MODEL

    MODEL

    Component

     

    Specifications

    1

    Duty Cycle

    System should be designed to automatically switch ON at dusk, operate throughout night and automatically switch OFF at down.

     

    PV Module

    1x75 Wp or 2x37 Wp. Vop 16.4 V, Voc 21 V.

     

    Lamp

    11 W CFL, either 4 – Pin or 2 – Pin Type with light output of 900 +/- 5% lumens.

     

    Battery

    12V, 75AH. Tubular Plate.

     

    Others Components

    Control electronics. Module mounting hardware. Battery box. Inter connecting wires. Swiches. Operation, instruction and maintenance manual.

     

       
    For Solar Generators:
       
      Model

    Model

    PV Capacity

     

    Estimated Cost

    Model – I

    150 Wp

     

    Rs. 45,000/-

    Model – II

    300 Wp

     

    Rs. 90,000/-

    Model – III

    450 Wp

     

    Rs. 1,35,000/-

    Model – IV

    600 Wp

     

    Rs. 1,80,000/-

     

       
             Notes
  •     Subsidy of 40% with an upper limit of Rs. 40,000/- will be provided on eachgenerator.
  •     User will also be eligible for loans on the balance cost of the solar generators.
  •     Subsidy will be released directly by MNES to the Manufactures.
  •     Subsidy will be released directly by MNES to the Manufactures.
  •  
    Q9.

    What is the pattern of central financial assistance?

     

      SPV Systems

     

    SPV Systems

    Central Subsidy

    Service

    Charge(Rs)

    a) 

    Solar Home Systems

    50% of ex.

    Works

    Cost. Subject to

    maximum

    of

    North-eastern

     Region

    90% of ex. Works

    subject to a

    Max. of

     

     

    18W Module, 1 light

    ¨    (1x18Wp PV module under STC,

    ¨    1x CFL ( 9w/11w),

    ¨    Battery: 1x12V , 20AH Tubular Plate Low

           maintenance type lead  Acid Battery

    ¨    Control electronics, module mounting

           Hardware, battery box, inter-connecting

           Wires/cables, switches,

           operation,instruction  And maintenance

           manual)

    3000

    5000

    200

     

    37W module , 2 lights

    ¨    1x37Wp PV module under STC,

    ¨    2x CFL ( 9w/11w),

    ¨    Battery: 1x12V ,40AHTubular Plate Low

           maintenance type lead Acid Battery

    ¨   Control electronics,module mounting

           hardware,battery box,inter-connecting

           Wires/cables, switches,operation,

           instruction  And maintenance manual)

     

    5500

    10000

    200

     

    37 W module, 1 light, 1 fan

    ¨    (1x37Wp PV module under STC,

    ¨    1x CFL ( 9w/11w),

    ¨    1Xdc fan (with wattage less than 20 W)

    ¨    Battery: 1x12V ,40AH Tubular Plate Low

          maintenance type lead Acid Battery

    ¨    Control electronics, module mounting

          hardware, battery box, inter-connecting

          Wires/cables, switches, operation

          instruction  And maintenance manual)

    5500

    10000

    200

     

    74W Module, 2 lights, 1 fan

    ¨    (2x37Wp PV module under STC,

    ¨    2x CFL ( 9w/11w),

    ¨    1Xdc fan (with wattage less than20 W)

    ¨    Battery: 1x12V,75 AH Tubular Plate Low

          maintenance type lead Acid Battery

    ¨    Control electronics, module mounting

          hardware, battery box, inter-connecting

          Wires/cables, switches, operation,

          instruction  And maintenance manual)

    10000

    18000

    200

     

    74W Module, 4 lights

    ¨  (2x37Wp PV module under STC,

    ¨  4x CFL ( 9w/11w),

    ¨  Battery: 1x12V,75 AH Tubular Plate Low

         maintenance type lead Acid Battery

    ¨   Control electronics, module mounting

         Hardware, battery box, inter-connecting

         Wires/cables, switches, operation,

         instruction  And maintenance manual)

    10000

    18000

    200

    b) 

    Street Lighting System

    11000

    20000

    -Nil-

    c) 

    Power plants & other

    community systems

    1,80,000/KWp of

    PV array capacity

    3,50,000/KWp

    of PV array Cap.

    10,000/-

    (power plants

    d) 

    Solar Generators

    40% withan

    upper limit of

    Rs.40.000/

    per generator

     

     

     

    150 Wp PV Cap.

    18000 Approx.

     

     

     

    300 Wp PV Cap

    36000 Approx.

     

     

     

    450 Wp PV Cap

    40000 Approx.

     

     

     

    600 Wp PV Cap

    40000 Approx.

     

     

     

       
    Q10.

     What is the eligible catagories of beneficiaries?

    Ans.
      SPV Systems

      SPV Systems

     

      Eligible Categories of Beneficiaries

     Solar Home Systems

      All Categories of individual beneficiaries & non profit Institutions /

      Organizations. No individual would be given more than one system.

     Street Lighting Systems

      All categories of non – commercial institutions / organizations, State Nodal

      Agency, Electricity Boards, Panchayats, Zilla Parishads and DRDA’s.

     SPV Power Plants  / Others

     Systems

      All categories of non – commercial institutions / organizations, State Nodal 

      Agency, Electricity Boards, Panchayats, Zilla Parishads and DRDA’s.

     

    Q11.  Is there any loan available?
    Ans. Yes, soft loans are available at an interest rate of 5% (individuals and other organizations) per annum and 7% (commercial borrowers who can claim depreciation benefits) and also Financial intermediaries who borrow funds from IREDA for on – lending at 5% or 7% rate of interest will be charged an interest rate of 2.5% or 4.5% respectively by IREDA. Such intermediaries will not be able to claim depreciation benefit and the on-lending arrangement will not be treated as a lease arrangement, through Indian Renewable Energy Development Agency Limited (IREDA). The minimum amount of soft loan will be Rs. 5 Lakhs for Direct User and Rs. 10 Lakhs for Intermediaries. The principal with the interest is repayable in 6 years (including one year moratorium) starting at the end of first year of sanction of the loan.
       
    Q12.  What is the performance guarantee for the system?
    Ans. The manufacturers must provide a warranty for a minimum period of 2 years for the complete SPV system (including the battery) and a minimum 10 years for PV modules from the date of supply. Annual maintenance Contract (AMC) for the SPV Systems should be for a period of 5 years including the warranty period.
       
    Q13.  What is the minimum loan eligibilty from ireda?
    Ans. Minimum loan for a project should be of Rs. Rs. 5 Lakhs for Direct User and Rs. 10 Lakhs for Intermediaries.
       
    Q14.   Who are the manufacturers and suppliers of spv water pumping systems?
    Ans.
     a)M/s. Photon Energy Systems
    1/482, Avanashi Road,
    Neelambur, Coimbatore – 641 014
    Phone: 0422 – 2627545, 2627003
    Fax: 0422 - 2628504
     b)M/s. Udhaya Semiconductors Ltd.
    Plot No. 775 – K, Road No. 45,
    Jublee Hills, Hyderabad – 560 033
    Phone: 040 – 23231685, 23231545
    Fax: 040 – 23546152, 23544839
     c)M/s. Central Electronics Ltd.
    4, Industrial Area,
    Sahibabad – 201010, Uttar Pradesh
    Phone: 0120 – 2895166, 2895165
    Fax: 0120 – 2895147, 2895148
     d)M/s. Surya Jyothi Devices Pvt. Ltd.
    E-3, Lajpat nagar - II
    New Delhi - 110 024
    Ph : 91-11-29814822, 29814129.
    Fax : 91-11-29819444
     e)M/s Tata BP Solar India Ltd.
    Plot No. 78, Electronic City
    Hosur Road, Bangalore - 561 229
    Ph : 080-8520082/3, 8520973/4
    Fax : 080-8520972/116
     and
     M/s Tata BP Solar India Ltd.
    70-73 UGF, World Trade Centre
    Barakhamba Lane, New Delhi - 110 001
    Ph : 011-23411537, 23411538
    Fax : 011-23411539
     f)M/s. Rajasthan Electronics & Instruments Ltd.
    2, Kanakpura Industrial Area
    Sirsi Road, Jaipur 302 012 Rajasthan
    Ph: 0141-352271, 354362, 63
    Fax : 0141-351926, 352841, 358808
     g)M/s. Titan Consultants & Services Ltd.
    16, Aruna Enclave, Trimulgherry
    Secunderabad - 500 015
    Andhra Pradesh
    Ph : 040-7742085
    Fax: 040-7795629
     h)M/s Premier Solar Systems (P) Ltd.
    41 S V Co-op Indl. Estate,
    Balanagar, Hyderabad - 500 037
    Ph: 040 – 23777521, 23777522
    Fax : 040 – 3771879
     i)M/s. Bharat Heavy Electricals Ltd.
    P. B. No. 2626, Mysore Road,
    Bangalore – 560 026
    Ph: 080 – 6744283
    Fax: 080 - 6740137