Q1.
|
What is the sectoral
eligibility for availing loan?
|
|
Ans.
|
Biomass Power:
The direct combustion power projects having capacity of 1
to 10 MW with minimum steam generation pressure of 63 Kg. / Cm2 are
eligible. However the IREDA loan will be restricted to 7.5 MW Capacity.
Biomass Cogeneration:
- Small scale Cogeneration Projects (except
sugar industries ) up to 7.5 MW installed
capacity with steam generation pressure of 63 Kg. / Cm2 are
eligible.
- The projects having above 7.5 MW installed
capacity (both for sugar and non-sugar industry) with steam generation pressure
of 63 Kg. / Cm2 are
eligible.
- IREDA also has additional / bridge loan
scheme for SDF supported Bagasse based Cogeneration projects in addition to its
normal scheme for term loan.
|
|
Q2.
|
Is DPR required to be prepared by a reputed consultant?
|
|
Ans.
|
Yes, Consultants, who are involving in the power sector,
are preferred.
|
|
Q3.
|
What are the appraisal requirements?
|
|
Ans.
|
Project
should have been registered with IREDA. Detailed project report along with cost
estimates and other relevant information & clarifications as requested by
IREDA should have been submitted / clarified.
|
|
Q4.
|
What are the eligibility requirements for availing loan?
|
|
Ans.
|
For
Eligibility Requirements please refer to the General Eligibility
Conditions of IREDA’s Financial Guidelines.
|
|
Q5.
|
What is the Security that is required to be furnished?
|
|
Ans.
|
For
Security Requirements please refer to Security (Project Financing Scheme)
of IREDA’s Financial Guidelines.
|
|
Q6.
|
How much time does it take for the loan to get
sanctioned?
|
|
Ans.
|
Normally, IREDA sanctions a project within 90 days of
registration of the same, provided complete details / papers are submitted by
the applicant and the project is found viable from technical, financial and
legal point of view.
|
|
Q7.
|
Who are the Suppliers / Consultants?
|
|
Ans.
|
Click
Here for the List…
|
|
Q8.
|
What is the capacity limitation?
|
|
Ans.
|
Biomass Power:
1 to 10 MW (However, IREDA loan will be restricted to 7.5
MW Capacity.
Biomass Cogeneration:
-
For Sugar Industry: above 7.5 MW
|